Karl Maria von Hacken-Phebe

3.13.2006

2006LE - preparation

Called III around 11:00 AM to make sure that there would be someone at III to do the step-around of the backup/restore tape step, since we do Legato backup to disk and don't need the tape backup. Ken was supposed to take care of it .c899359, but it hadn't been done by the time I got over to the machine room in Hubbard. Grr. Called III and talked to my favorite helpdesker (Glenn) and he got us stepped around. Details of the preparation phase:

2:57 PM... loading main software
3:00 PM... installling - loading additional software upgrade
3:06 PM... installing - loading software utilities
3:09 PM... installing - loading new system files
3:18 PM... installing new system files
3:20 PM... building library routines - 0%
3:28 PM... building library routines - 25%
3:34 PM... building library routines - 50%
3:45 PM... building library routines - 75%
3:50 PM... build completed
3:50 PM... phase 1 finished

In 30 minutes, I'll go and finish the job, Pardner. Swagger... swagger... stumble?

0 Comments:

Post a Comment

Links to this post:

Create a Link

<< Home